1. Introduction
2. Design Considerations
3. Operation and Maintenance
4. Record/Documentation
5. Appendix A:Sample Checklist for Inspection and Testing of Solar Water Heating Systems
Appendix A: Sample Checklist for Inspection and Testing of Solar Water Heating Systems
Installation Address: ________________________________________
(a) Solar Collectors | Tested by/Date (N/A if not applicable) | |
---|---|---|
(i) | Clean the collectors (when they are cool) to remove dust, debris and other contaminants on the collector surface. | |
(ii) | Check the collectors for cracked, broken or deformed glass, shading, deterioration of absorber paint/coating, tubes and insulation. | |
(iii) | Check the surface temperature of the absorbers for abnormal temperature. | |
(iv) | Check for excessive condensation or outgassing under glazing. | |
(v) | Check the frames for corrosion. | |
(vi) | Check the earthing conductor conditions of collectors with sensors. | |
(vii) | Test the flow rate for compliance with manufacturer’s recommendations and the temperature of each collector group in the array. | |
(viii) | Check the absorbers and pipes for any leakage. | |
(ix) | Remove scaling inside pipework. |
(b) Supporting Frames | Tested by/Date (N/A if not applicable) | |
---|---|---|
(i) | Check the physical connections and fixing components to make sure the solar collectors and pipework are securely fixed. | |
(ii) | Check all hardware for signs of corrosion; remove rust; re-paint and replace if necessary. |
(c) Solar Collector Arrays | Tested by/Date (N/A if not applicable) | |
---|---|---|
(i) | Check for abnormal position and movement of solar collectors. | |
(ii) | Check hot water flow rate of collector arrays. |
(d) Heat Transfer Fluid | Tested by/Date (N/A if not applicable) | |
---|---|---|
(i) | Check heat transfer fluid conditions, concentration and degradation for indirect type; refill heat transfer fluid if necessary. | |
(ii) | Check the water quality for direct type. | |
(iii) | Check that provisions are made for draining and filling the system (air vents, drains, pipes are correctly graded in-between). |
(e) Pipework | Tested by/Date (N/A if not applicable) | |
---|---|---|
(i) | Check pipework for signs of cracks, defects and leaks, damage, blockage, or degradation of thermal insulation. | |
(ii) | Inspect for signs of defects, sagging, cracks; replace if necessary. | |
(iii) | Check the air locks or blockages of the pipework. | |
(iv) | Check signs of deformation not holding slopes to drain. | |
(v) | Check for abnormal operation temperature; stop circulation in the collection loop and release the excessive pressure inside pipework if any. | |
(vi) | Remove scaling from pipework. |
(f) Valves | Tested by/Date (N/A if not applicable) | |
---|---|---|
(i) | Check valves for any damage, leakage, getting stuck or signs of corrosion; check valve settings and valve position. | |
(ii) | Test operation according to the O&M manual and manufacturer's recommendations. |
(g) Strainers | Tested by/Date (N/A if not applicable) | |
---|---|---|
(i) | General cleaning and check for signs of corrosion and getting stuck. |
(h) Heat Exchangers | Tested by/Date (N/A if not applicable) | |
---|---|---|
(i) | Check heat exchangers for signs of leakage or corrosion and the associated supports. | |
(ii) | Test flow rate for compliance with manufacturer’s recommendations. | |
(iii) | Remove scaling from heat exchangers. |
(i) Thermal Storage Tanks | Tested by/Date (N/A if not applicable) | |
---|---|---|
(i) | Check storage tanks for cracks, leaks, rust or signs of corrosion. | |
(ii) | Check the insulation for damage or degradation. | |
(iii) | Check the system pressure and temperature; depressurise the excessive system pressure if any. | |
(iv) | Discharge water inside. | |
(v) | Remove scaling from thermal storage tanks. | |
(vi) | Check that provisions have been made to prevent reverse heating of the solar thermal storage by the domestic hot-water back-up heater. | |
(vii) | Check the thermostat and control of the backup heating element if backup heating is provided. |
(j) Expansion Tanks | Tested by/Date (N/A if not applicable) | |
---|---|---|
(i) | Check the expansion tanks with diaphragms in by briefly depressing the Schrader valve for leaks of fluid. |
(k) Pumps | Tested by/Date (N/A if not applicable) | |
---|---|---|
(i) | General cleaning and re-paint. | |
(ii) | Check that the electrical connections are securely fastened and the earth bonding conductors are properly connected. | |
(iii) | Check the piping connections for leakages. | |
(iv) | Lubricate the moving parts. | |
(v) | Check that the pumps are operating correctly, without abnormal movement or water leakage. | |
(vi) | Check the pressure and flow to ensure the operation condition of the pump is in order. |
(l) Make-up Water Tanks | Tested by/Date (N/A if not applicable) | |
---|---|---|
(i) | Drain and flush out the tank to remove sediment. | |
(ii) | Check the water tank for cracks, leaks, rust or signs of corrosion. |
(m) Controls, Sensors and Meters | Tested by/Date (N/A if not applicable) | |
---|---|---|
(i) | Check operational indicators of temperature and pressure to ensure proper operation of the pump and controls. | |
(ii) | Check the sensor wiring for avoidance of losing connection. | |
(iii) | Check the accuracy of the sensors and controls; re-calibrate if necessary. | |
(iv) | Check that controls, water level sensors, temperature sensors are operating sensibly. | |
(v) | Open pump control panel box and check that no fuses/ MCBs have blown and that all electrical connections are tight. | |
(vi) | Check pump control panel for water incursion and corrosion damage. | |
(vii) | Conduct functional tests of the pump panel control. | |
(viii) | Conduct functional tests of isolation switches and protection devices for the pump panel control. | |
(ix) | Check ventilation condition and dust cleaning from heat rejection fins. | |
(x) | Check and make sure the valve is not stuck or closed. |
(n) Safety and Warning Notices and Labels | Tested by/Date (N/A if not applicable) | |
---|---|---|
(i) | Check for warning signs and labels and replace if necessary. | |
(ii) | Check the tags or labels which indicate the positions or flow direction at each valve and pipe. |
(o) Instruments | Tested by/Date (N/A if not applicable) | |
---|---|---|
(i) | Check the monitoring instruments (e.g., temperature sensors) to make sure they are operational. | |
(ii) | Calibrate instruments by an accredited laboratory. Replace instruments, temperature sensors, and meters as necessary. |
(p) System Monitoring and Data Logging Systems | Tested by/Date (N/A if not applicable) | |
---|---|---|
(i) | Monitor the operating status, flow rate, temperature, alarms and alert parameters. | |
(ii) | Check the Building Management System for solar water heating system; check the hardware for signal interface and upgrade software as necessary. | |
(iii) | Maintain a log of cumulative electrical energy consumption (kWh to date), operating temperature and flow rate against date. | |
(iv) | Check the monthly mean in-plan solar irradiation, monthly mean solar energy absorbed by the system and monthly electrical energy consumption of the circulation pump. |
Subscribe for future updates
In order to subscribe to the newsletter or to activate e-mail notifications and content updates, you can follow few simple steps described below.It allows users to receive customized e-mail notifications when content is added or modified in EMSD.
Subscribe
x
Subscribe for future updates
We will only send you emails about the update that you subscribe to, and you can unsubscribe at any time.